What are the relevant issues to pay attention to in the process of hazardous waste disposal?


  What are the relevant issues to pay attention to in the process of hazardous waste disposal?

  1. Let's start with the EIA.

  The EIA specifies what is hazardous waste, how much, and which qualified disposal unit to sign an agreement. Because the state has increased the penalties for EIA, companies want to write less EIA (not to write may not write) will face legal risks. In addition, the amount of EIA written less means that the total amount of legally disposed waste is less.

  2. declare the program to the local environmental protection bureau one year in advance (according to the agreement signed between the EIA and the disposal unit, declare the approximate quantity, species, disposal month, etc.)

  3. Inform the disposer when hazardous waste occurs, negotiate the disposal price with the disposer, and sign a contract for the disposal of that batch of waste.

  4. The general hazardous waste disposer will contact a qualified hazardous waste transportation unit and ask the unit to negotiate the transportation price and sign a transportation contract with the generator. Then the generator will request and obtain a request from the local Environmental Protection Bureau where the disposer is located, and obtain the quintuple and number according to the qualification of the delivery unit and the delivery contract, the qualification of the disposer and the disposal contract of this batch of hazardous waste and the hazardous waste program. Note that each vehicle and each type of hazardous waste in five copies. In practice, the disposer requires five copies more professional and convenient.

  5. The disposer or auditor will inspect and escort the shipment at the occurring party, and the transporter will load and transport the shipment to the disposer. First fill out five copies (there are actually seven) and stamped, delivered to the unit to confirm the signature and shipped out. di a copy is retained by the producer, the second copy to the local environmental protection bureau. The other di copy paper, second copy paper and 345 sheets of paper are brought to the disposal party by the delivery unit or escort. A check is correct after signing and stamping, the third link sent to the shipping unit; di a link and the second link returned to the producer, the producer will be the second link to the local environmental protection bureau; the fourth link is retained by the disposal side itself, the fifth link to the disposal side of the local environmental protection bureau. In practice, the producer well keep di copy and returned di copy, the carrier retains the third copy, the disposer retains the fourth copy, and the second and fifth copies are sent by the disposer to the respective EPA.

  6. Hazardous waste disposal fee is an operating service charges, following the principle of "who commissioned, who pays; who services, who charges", the generator should be qualified units to dispose of hazardous waste, and pay the disposal fee.

  Hazardous waste disposal in accordance with the different disposal methods charge. Landfill disposal 2.2 yuan / kg, can be up 20%, can also be down. High temperature disposal 2.80 yuan / kg, can be floated up 30%, down unlimited; physical chemical disposal is 1.8 yuan / kg, can be floated up 30%, unlimited down; pharmaceutical disposal shall not exceed 70 yuan / kg.

  In China, the road of hazardous waste disposal needs to continue to move forward, and enterprises need to explore new technologies and management methods to achieve greater social and economic benefits in the disposal of hazardous waste.